Background:
Dhaka Metropolitan city has now been turned into the busiest densely populated city. Large number of people reside permanently in Dhaka city for service, business and other purposes. The dwelling places required for these large number of people are very inadequate. As a result, the residential areas of Dhaka city are getting overcrowded and dirty day by day and creating unhealthy environment causing damage to the beauty of city. All these are because of mainly unplanned urbanization. It is possible to reduce the pressure of population of Dhaka is a great extent by developing Flats/Apartments as a permanent resident. Focusing the need of housing for lower and middle income group of people, as promised by the Hon’ble Prime Minister, the Ministry of Housing and Public Works takes initiative to build several multi-storied residential complexes around Dhaka city through planned urbanization.
This Project had been accepted categorically by ECNEC under Uttara 3rd Phase Project, RAJUK on 25th April, 2000. In line with the categorical acceptance a Development Project Proposal (DPP) for construction of around 22000 apartments for middle and lower income group of people at sector-18, Uttara, Dhaka has been recommended at inter-ministerial meeting at ministry of Housing and Public Works on 28th February, 2010.
Hon’ble Prime Minister has laid Foundation Stone of the Project on 21st April, 2010. DPP of the Project has been approved on 10th October, 2011. Project Duration: Nov/2011 to June/2016. It is the ever largest Planned Apartment Project in the country having 214.44 acres of land at Uttara 3rd Phrase Project, Sector-18, Uttara, Dhaka for Low and Middle Income group of people. Approximately 240 nos. 16 storied Apartment Building including one basement floor comprising about 20,160 nos flats were supposed to be constructed. The statistics of Building and flats as per approved DPP are as follows:
Block |
Flat Size |
Nos of Buildings |
Unit per Floor |
Total Flats |
Block 'A' |
Net : 1250 sft |
79 |
6 nos |
6636 |
Block 'B' |
Net : 1050 sft |
86 |
6 nos |
7224 |
Block 'C' |
Net : 850 sft |
75 |
6 nos |
6300 |
Total |
240 nos |
20,160 |
Project Cost : Tk. 903071.87 Lacs
Project Duration : November/2011 to June/2016.
Location of the Project:
'Uttara Apartment Project' is situated at sector 18 of Uttara 3rd Phrase Project covering Block 'A', 'B' & 'C'. The main approach is from Ashulia-Mirpur Flood Protection Embankment Road and Sonargaon Jonopath of Uttara Model Town. There is a plan in future, this project approach will be connected directly to the Jashim Uddin Road of Uttara Model Town. In addition, there are two stations of MRT (Central & South) within the range of walking distance of the project area.
Objective of the Project:
Implementation of Block-A
Department of Architecture (DoA) and Public Works Department (PWD) have been responsible for preparing all designs and drawings of the project. According to their design, tenders were called in 2012 in a conventional manner for 79 nos 16-storied buildings of Block-A. It may be mentioned here that out of 79 buildings, 39 are under the responsibility of PWD for implementation. Due to the failure of the employed contractors and not achieving any visible progress for more than two years, all the contracts were cancelled in 2014. Subsequently, construction work of this block was started again in 2014 with the appointment of new contractors.
The Hon’ble Prime Minister Sheikh Hasina inaugurated the buildings of Block-A of the project through video conferencing on the 1st November, 2018.
Implementation of Block-B & C
A Memorandum of Understanding (MoU) was signed with the Special Envoy Office of Malaysian Government on October/2011 for implementing Block-B & C with Technical and Financial assistance in design-build-transfer mode. The methodology of construction was supposed to be Industrialized Building System (IBS) with aluminium formwork having shear wall framing technology. After being expired, a Revised MoU was signed on April/2014 making clear all financial arrangements. That is, “The Special Purpose Vehicle (SPV) assigned by Malaysian Government shall be solely responsible for the entire costs and expenses to the project in compliance of prevailing Rules and Standard Procedures of Bangladesh”.
In Malaysian offer, they propose net 1250 sft of flat size at Block-B and 1050 sft at Block-C instead of 1050 sft and 850 sft of respective blocks in approved DPP. That’s why DPP needs to be revised. Meanwhile, the project validity period was extended upto June/2018 without increasing cost. According to that 1st revision of DPP incorporating all necessary issues, such as: flat size, procurement mode (G to G) of Block-‘B’ & ‘C’ and duration of the project was sent to Ministry for approval from ECNEC.
The RDPP(1st) of the project, for implementation in the period from November/2011 to December/2020, was approved by Hon’ble Prime Minister on 31 October 2017, subject to compliance with the following condition:
“In revised project proposal, construction of 850sft flat size should be included instead of 1050sft in Block-‘C’”.
To comply above condition, necessary data and information are included in RDPP and after detailed examination, it has got approved from Ministry of Planning on April/2018. The statistics of Buildings and flats as per approved RDPP are as follows:
Block |
Flat Size |
Nos of Buildings |
Unit per Floor |
Total Flats |
Block 'A' |
Net : 1276 sft Gross : 1654 sft |
79 |
6 nos |
6636 |
Block 'B' |
Net : 1250 sft Gross : 1641 sft |
52 |
6 nos |
4368 |
Block 'C' |
Net : 850 sft Gross : 1220 sft |
52 |
6 nos |
4368 |
Total |
183 nos |
15,372 |
Project Cost : Tk. 1058628.29 Lacs
Project Duration : November/2011 to December/2020
November/2011 to June/2022 (Time extended without increasing cost).
Design & Supervision:
Project Facilities:
a) Approximately 55% of the land area of the entire project has been kept open for playgrounds, parks, greeneries, roads etc.
Facilities Inside the Building & Apartment:
Current Progress:
Sl No. |
Date : Flat ID Given |
Total Flats |
1. |
September/2017 |
837 nos |
2. |
January/2018 |
2621 nos |
3. |
March/2019 |
797 nos |
4. |
November/2020 |
306 nos |
5. |
September/2021 |
647 nos |
Total = |
5208 Nos |